What is Takt Time?

Available production time divided by customer demand. For example, if a factory operates 480 minutes per day and customer demand is 240 units per day, takt time is two minutes.

Meaning and application in management

Available production time divided by customer demand.

For example, if a factory operates 480 minutes per day and customer demand is 240 units per day, takt time is two minutes. Similarly, if customers want two new products per month, takt time is two weeks. The purpose of takt time is to precisely match production with demand by providing a rhythm for the production system. It is the heartbeat of a lean system.

See: Cycle Time, Heijunka, Just-in-Time Production, Operator Balance Chart, Pacemaker Process, Pitch, Takt Image.

Keep learning with the lean vocabulary

Explore related terms and go deeper with real-world analyses by our industry leads.

Related term

Cell

A location where the processing steps for a given item take place immediately one after another, so that parts…

View term
Success story

The Help Chain for Maintaining Production Stability

See how this concept and management mindset were applied in practice to deliver real business results.

Read the full article
Hands-on training

Lean no Gemba Introdução prática e presencial

Build leadership and problem-solving skills at the gemba with support from our specialists.

See the training