Applying lean in process industries
The food, chemical, pharmaceutical and cosmetics sectors, which are essentially process industries, have been successful in applying lean concepts, achieving impressive results such as lead time reductions of up to 60%, a 40% reduction in setup time, improvements in delivery performance of up to 30%, as well as capacity gains that reach 30% in some product families.
This article will present which implementation strategy can be adopted and the results that can be achieved by applying lean concepts in a process industry. A process industry is understood as one in which production takes place through physical-chemical reactions triggered by mixing reagents or by changing parameters that influence how the final product is obtained.
A hypothetical example of application in a process industry that works in batches will be presented. The analyses and recommendations presented are based on my 4 years of experience applying lean in several real cases of process industries with similar characteristics.
1. Understanding the need
When starting the lean journey, one of the critical success factors is a clear understanding of what the company needs. What are the critical factors for the business in terms of delivery, quality and cost? What are the objectives to be achieved? Which products are associated with these objectives?
Answering these questions gives us a direction that allows us to focus the initial work on the process that is aligned with the needs of the business. In the hypothetical example presented below, the business need is to improve delivery and free up capacity for new business.
2. Defining the product families
Once the business need has been defined, we must identify which products affect the indicators associated with this need, using a product family matrix. A product family is defined by products that go through the same processes (physical steps).
To build this matrix it is necessary to identify the products and the equipment in each process, then place an “X” on the equipment the product should preferably go through and, if there is an alternative, use the letter “A” to identify it. In this way, we can identify which products have similar processes, as in the example in Figure 1.
This matrix should make it possible to identify on which equipment the product is processed. Some companies do not define on which equipment the product is processed, seeking flexibility and assuming that the product can go through any equipment in the process in question, which results in not fully using production capacity.
When carrying out a careful analysis, we see that there are some factors whose differences are significant, such as setup time, cycle time and even the number of operators required. These factors should serve as a guide for grouping into product families, since products with similarities in these factors should be part of the same family.

3. Understanding the current situation
We should begin by developing a view of the current production system, for which we use Value Stream Mapping (VSM), in which the information and material flows for a product family are defined. In this way, we can carry out system kaizen. The traditional method of walking the process and drawing the map with real data observed at the gemba should be followed.
In Figure 2, we present a typical value stream map of a process industry, consisting of weighing; processing of the product, where mixing usually takes place, generating the chemical reaction that gives rise to the final product; testing (quality control), whose function is to check the product’s characteristics and define product adjustments; filling, where the product is packaged for storage and delivery to the end customer.
The manufacturing process represented in the value stream map is relatively simple, and the processing time is 44.5 hours to manufacture one batch. This type of industry usually has a long lead time, which in this example is 122 days due to large manufacturing batches, which are the result of long production campaigns.
The high inventory at the ends, raw material and finished product, is the largest contributor to this long lead time, since work-in-process inventory (WIP) tends to be comparatively low. Regarding finished product inventory, a root cause is the long production campaign (EPEI - every product every interval > monthly), which is set because of very long setup times (identified in the map above), which are the root cause of the problem and must be addressed in the future state design.
In the case of raw material, there are two factors that generate high inventory: the first is the low delivery frequency of the supplier, in some cases as infrequent as every two months, and the second is the practice of purchasing materials in a push manner, without observing the plant’s actual consumption, bringing excess material into the company.
Another problem highlighted in the current state map is the long testing time for quality control, whose main causes are: batch work, where the operator runs tests on batches of samples rather than one by one, generating waiting since the first sample tested waits for the others to be finished; and changes in the production sequence without respecting FIFO, also generating waiting.
From the equipment point of view, low availability is a common problem in this type of industry, in some cases reaching levels below 70%, often due to a lack of preventive maintenance.
In addition to availability, the size of the equipment is a critical factor that makes it unfeasible to work with smaller production batches, since such equipment is designed to work with a small mix and very high volume, conditions that are uncommon in today’s reality. We will adapt to it, as it is unthinkable to replace it without major investment, something companies do not have when starting the lean journey.
Another point that deserves attention is the change in production sequence along the process, made because of urgent orders or shortages of raw materials or packaging. The lack of a predefined sequence and of control causes these changes along the process, generating long waits in the value stream.
4. Establishing the future situation
The needs of the business should guide the establishment of the future situation, which in the case used as an example are increased capacity and improved delivery. The use of process capacity is often affected by the lack of rhythm in production, which causes stoppages and waiting along the process. In order to establish a rhythm in production, it is necessary to determine the takt time, the first step towards better use of production capacity.
4.1. Defining the production rhythm through takt time
Takt time is the rhythm set by the customer and is determined by dividing the available time by demand. In the process industry, available time is easily determined, considering the total time available per day minus planned stoppages (lunch, breaks and planned maintenance).
Demand should be defined based on a clear understanding of the sales volume of the product family in question. A very common mistake is to use production capacity to determine demand, whereas the correct approach is to use sales volume. Sales history is a reference for determining takt, but we must also consider the forecast for the coming months, anticipating a possible increase or decrease in demand in the short and medium term.
Let us consider the following example: demand is 10,000 liters of product per day, in total, for the selected product family. Available time, after deducting planned stoppages, is 15 hours per day (2 work shifts). The calculated takt time is:
Takt = 15 h / 10,000 liters = 900 min/10,000 liters = 0.09 min/liter or takt = 90 min/1000 liters
In other words, every 90 minutes the customer buys 1000 liters of product, which is the rhythm that should guide production. Using this number directly as a reference for production may not be practical, and in this case the image of takt time should be used: the “pitch”, which is determined by multiplying takt time by the quantity of product in the package (or batch).
Using this premise, let us calculate the “pitch” for each step of the process, starting with filling. In this case the pallet is a good reference for production, so assuming we have 1000 liters on a pallet, takt time itself can be used as the reference: Takt = 90 min/pallet. This means that every 90 minutes filling has to release one pallet.
Another possibility is to use the manufacturing batch, assuming that the manufacturing batch is 2000 liters:
Pitch = 0.09 min/liter x 2000 liters = 180 min/batch
Every 180 min production has to release one batch (2000 liters).
In Testing (laboratory), samples are handled, usually associated with a manufacturing batch (2000 liters); in this case we would have:
Pitch = 0.09 min/liter x 2000 liters = 180 min/batch = 180 min/sample
In processing and weighing, the reference used is the manufacturing batch, whose “pitch” determined for this example is 180 min/batch.
The different forms of takt image – minutes per liter, batch, pallet, sample – are devices to make the rhythm visible and allow it to be followed during the workday and not at the end of the day, as usually happens. The most important thing is that the rhythm is the same for the entire manufacturing process from beginning to end.
Once takt time has been defined, we must start monitoring the production rhythm in relation to this time, and for this we use the production status board (Figure 3). It allows hour-by-hour monitoring of production, exposing problems related to not meeting the customer’s rhythm.
Production control in this type of industry usually consists of checking the volume produced at the end of the day, week or month. This type of control does not allow immediate corrective action, leading to large losses during the manufacturing process. Hourly production control is a fundamental mechanism for enabling a problem to be solved quickly, ensuring the result at the end of the day.
By applying this type of control, it is possible to detect the lack of stability of a value stream, common in the process industry, caused by instability in the 4 M’s (Manpower, Material, Machine and Method).

To analyze and solve the problems identified by the operator during the work shift, a help chain was created with the aim of taking immediate action to stabilize production. See the article on the Help Chain.
When analyzing the current state map, bearing in mind the need to increase capacity, we found that the availability of the processing step is low (70%). To increase this availability to 85%, it is necessary to collect stoppage data over a month of work, build a Pareto of stoppages, apply the 5 whys to identify the causes of each significant stoppage, implement countermeasures and carry out preventive maintenance to prevent the stoppages from recurring.
Another factor that affects capacity is long setup time. With the aim of reducing setup time, the implementation team planned a kaizen in the processing step, with the goal of reducing setup time from 8 to 2.5 hours. To achieve these results, the following steps were followed:
A) Identifying internal and external activities. Internal activities are those that can only be carried out when the equipment is stopped, and external activities are those that can be carried out with the equipment running;
B) Separating internal from external activities, so that external activities are carried out before the equipment stops;
C) Reducing the time of internal activities by preparing devices and improving the process;
D) Reducing the time of external activities by applying 5S, bringing tools closer to the point of use, identifying tools, etc.;
E) Standardizing the setup and training.
It is worth remembering that the goal of reducing setup time is not only to increase capacity but, above all, to make it possible to carry out more setups, in shorter times, in order to reduce the size of the manufacturing batch, determining the new EPEI (Every Product Every Interval), such as Every Product Every Week (weekly batches).
4.2. Improving delivery through the pull system
When analyzing the performance of the process with regard to delivery (70% delivery performance), with the high level of inventory, one would have expected delivery performance to be better, but this was not the case. Despite having large inventories, the company had an unbalanced inventory with products that were not being demanded by the customer. With the aim of improving delivery without increasing inventory, the company decided to implement a Pull System.
Implementing a pull system is a systemic change, in which the planning logic moves from a push system, in which production is planned based on a forecast, to planning based on actual demand (customer pull).
In process industries, forecast-based planning is frequent, generating large quantities of finished product inventory. Implementing a pull system follows the same lines as in discrete parts manufacturing: replenishment lead time, setup times, machine breakdowns, demand variation and consumption frequency must be considered to determine the size of the supermarket. The supermarket is made up of 3 elements (cycle, buffer and safety stock). (See the LIB workbook "Creating Level Pull" by Art Smaley).
When sizing the system it is essential to identify which products will be produced through kanban, usually those with the most frequent consumption, and which products will be MTO (Make to Order), with less frequent consumption. Based on this definition, equipment use should be planned so as to allow both MTO and kanban products to be produced within the predefined leveling, if possible every day, in order to avoid product shortages for delivery.
Another important point when sizing the pull system is that, for some low-demand products, the minimum batch imposed by the equipment may be very large, representing months of consumption of that product. In this case, strategies of creating separate product families, with smaller equipment (mixers, vats, etc.) for these products, are useful, thus allowing smaller batches to be produced.
In the example, the company decided to implement pull for finished products and for raw material. With regard to pull of finished products, the company worked very hard to reduce setup time, as described above, since the goal of reducing inventory from 70 to 20 days would require the factory to cut its setup times by up to 3 times, that is, from 8 hours to 2.5 hours.
This setup reduction strategy allowed the production campaign to be reduced from 60 days to 20 days, which means producing the entire product cycle in 20 days (EPEI – Every Product Every Interval). Another important factor was the standardization of manufacturing batches, adjusted according to demand, which created stability for production, since batches did not change in size, allowing the operator’s work to be standardized.
In the case of raw materials, the initiative planned in the future state was the implementation of pull with a pilot supplier, establishing a trigger point in the raw material inventory that triggers replenishment by the supplier. To start pull, they decided to adopt a conservative strategy of keeping a maximum of 30 days of inventory until the system stabilized.
4.3. Scheduling the pacemaker process
Production scheduling should be done at the pacemaker process. Normally in process industries, the pacemaker process is the first step of the process, weighing.
The great difficulty is that weighing is a shared area serving several product families, which means the schedule is changed through constant interference coming from various production processes.
In this case it is necessary to create a mechanism that prevents changes to the schedule, such as establishing the weighing takt. Based on the takt of each product family served by weighing, we can define the total number of batches needed per day, which is the total demand on weighing. In this way, we can size the weighing takt time and create limits on batches per day or per shift for each product family.
With these limits established, planning defines which batches should be weighed and in what sequence for each product family. Weighing will supply material according to the takt rhythm of each product family without excess, since the FIFO will limit the batches to be manufactured. If the FIFO is full, weighing stops picking material until the next step pulls the next batch, allowing a new batch to be placed in the FIFO.

Ensuring the sequence along the process is essential to guarantee replenishment of the product in the supermarket on time and without delays. It is necessary to create a mechanism that allows the product to be controlled along the process so that there is no waiting.
In the example in question, the product is transferred from one step to the next using mobile equipment. From a flow point of view, ideally one step would be next to the other, making it easier to transfer the product from one step to the next one unit (batch) at a time, avoiding motion and waiting. However, in the example, the areas worked in batches: weighing weighed several batches and sent them to the next step. Quality control, to optimize its work, prepared several samples at once and then released a batch of samples.
To establish a unit rhythm between the areas, FIFOs with a defined maximum quantity were created. The supplying process cannot produce if the FIFO is full, preventing inventory from building up between steps. When the customer process withdraws a batch from the FIFO, according to takt, the supplying process has to make a batch, thus ensuring the rhythm.
Since it was not feasible to change the layout, it was decided to create FIFO lanes between the process steps, making it possible to connect them (Figure 4). FIFO is a mechanism that physically and visually ensures that there is no change in the manufacturing sequence between process steps. This mechanism makes it possible to control the process lead time.
Another point where we should apply the FIFO concept is quality control, with a focus on reducing testing time, a critical point for the manufacturing process; in addition to FIFO, the cell concept can be applied, and administrative processes can be improved by identifying waste through administrative mapping.
As a result of the discussions above, the first future state was drawn as shown in Figure 6. Other improvement opportunities can be identified in the value stream map, but for the company’s needs, the points discussed so far were crucial to achieving the results in terms of capacity and delivery.
4.4. Results
In the example presented, the results achieved after implementing the actions were the following:

The results of the implementation are very similar to those in conventional industries, and the initial steps presented here are only the beginning of the journey, typically 9 months to a year of work.
5. Conclusion
The implementation of lean concepts in the process industry was shown through an example that highlights the typical characteristics and situations of this industry. The most significant change from the process industry’s point of view is related to establishing rhythm through takt time, an element little used in companies, which enables better use of resources.
Applying the concept of pull production is also a radical change in the way the company plans and schedules production, which requires discipline and persistence to implement.
There are also some typical paradigms in the process industry that need to be broken, such as: long setup times, long production campaigns and the push system.
The next steps should be linked to reducing EPEI, by reducing setup times, implementing problem-solving mechanisms and standardized work, and reducing process times, especially those related to the quality control area.