Metrics for production stability

Production Stability is the situation in which the production process or flow is kept within plan, from the standpoint of takt time and the behavior of the 4M’s. There are many ways to measure whether a process or flow is stable.
This article aims to point out the indicators for tracking production instability, as well as the ways of measuring, communicating and intervening in order to reduce waste and solve problems. We will present how this was done at Toyota do Brasil (see the article “Production stability at Toyota do Brasil”), both with process indicators and at the plant level.
1. MEASUREMENT AND INDICATORS AT THE PROCESS LEVEL
For each basic process such as stamping, body assembly, machining, painting, heat treatment, injection molding, etc., the supervisor and the immediate manager prepared the “Daily Production Report”, consisting of 5 A4-size sheets, in which basically the following indicators were measured:
- Quantity produced (volume produced according to the monthly production plan);
- Productivity calculation based on the number of hours available given the labor assigned to that day's production;
- “Downtime” (hours during which production stopped due to some type of waste or problem);
- Absenteeism and training (multi-skilling);
- Quality.
On the first sheet (see figure 1), the basic data recorded was the quantity produced, with the production tracking board reproduced at the bottom for hourly observation of any irregularities. If waste or problems did not occur, the planned production was achieved (see the problem tracking board and the necessary reactions in the articles: “The help chain” and “How to operate an andon”).

Figure 1: Daily production report
On the second sheet (see figure 2) we calculated productivity as in the example below, using the data from the first sheet:
(I) Volume produced in the day: 20 parts
Taken from the first sheet, with the possibility of producing fractions of units, since when the production period ended a part could be partially completed.
(II) Productive labor:
(A) Total labor in the area: for example, 27 people x 10 hours = 270 hours
(B) Overtime in the period: 18 people x 2 h = 36 hours
(C) Hours of non-productive staff in the area (supervisor helped): 1.5 h
(D) Overtime of non-productive staff: 0 h (not added)
(E) Late arrivals and early departures of labor (added up): 3.0 h
(F) Absences and vacations of labor (added up): 8.4 hours
(G) Total = A + B – C – E – F = 274.5 hours
(III) Labor for replacement parts:
(H) Hours allocated: 2.0 hours
- Note: If there were other types of special parts production, they were entered as (I), (J), (K), (L)
(M) Total = (H) + (I) + (J) + (K) + (L) = 2.0 hours
(IV) Non-productive activities: both machines and people standing idle
(N) Maintenance:
(O) Training: 5.0 hours
(P) Meetings: 1.82 hours
(Q) Improvements: 4.0 hours
(R) 5S: 13.37 hours
(S) QCC:
(T) Try-out: 4.2 hours
(U) Other:
(V) Total: = (N) + (O) + (P) + (Q) + (R) + (S) + (T) + (U) = 28.39 hours
(V) Productive hours:
(W) = (G) – (M) – (V) = 244.11 hours
(VI) Productivity calculation:
(X) Volume produced = 20 parts
(Y) Net productivity = (W) / (X) = 21.21 hours/part
(Z) Gross productivity = (G) / (X) = 13.73 hours/part
In this way, by observing the difference between gross and net productivity, we knew that the difference was idleness (labor waste) and how many hours were spent to produce one unit. This analysis was carried out daily by all areas.

Figure 2: Calculation of gross and net productivity
On the third sheet (see figure 3), “downtime” was analyzed by observing the production tracking board, and using the “Ishikawa Diagram + 5 Whys” the supervisor analyzed the problems detected, identified the root cause, and a possible countermeasure was determined by the supervisor. It is important to stress that before this phase (when the problem has already happened), the area leader was responsible for taking emergency action.
Figure 3: Downtime analysis
On the fourth sheet (see figure 4), the area's absenteeism and level of training (versatility matrix) were analyzed. When holding the daily 5-minute meeting, the leader used the kanri-ban to assign people and recorded on this sheet the discrepancies between what the workstation required and who occupied that workstation. This procedure was carried out to identify how often such problems occurred and thus eliminate the problem with the appropriate training for the employee.

Figure 4: Multi-skilling analysis
On the fifth sheet (see figure 5), the quantities of defective parts were recorded, along with the location and type of problem that generated the error.
Figure 5: Analysis of production defects
All this data was collected daily and sent to senior management for analysis, coming back signed, and on the same day the data was entered into the system by those responsible (supervisors) for each area. If there were errors or revisions, they went back to the production area's management and were returned for a new review.
The Production Planning and Control (PPC) Department, based on the data and indicators from all areas, prepared a monthly A3 (see figure 6), which was sent to headquarters and to the executive boards involved.
2. MEASUREMENT AND INDICATORS AT THE PLANT LEVEL
In an A3 format (see figure 6), the PPC Department prepared the Monthly Report (“Monthly Report”), with the following topics: General Information, Production Status (indicators), Key Points and Outlook.

Figure 6: Stability indicators
In the “General Information” field (see figure 6, item “a”), planned vs. actual production, the year-to-date total, adjustments to the production schedule due to changes in sales, and whether or not takt time needed to be readjusted were observed.
In the “Production Status” field (see figure 6, item “b”), the indicators measured monthly were made available, such as:
- Production of approved vehicles (units/month),
- Production of replacement parts and parts for other plants (units/month),
- Partial productivity of each process and the cumulative productivity for the standard or highest-volume product (man-hours/unit),
- Accident levels (frequency), with this data being handled by the Safety area together with Production, through A4 forms filled out by supervisors and leaders whenever accidents occurred,
- Quality levels (average defects/unit),
- Execution of planned vs. actual investments, with this data being handled by each responsible area, through A4 forms filled out by supervisors and leaders whenever investments were or were not carried out,
- Cost reduction by process (value/unit), also through A4 forms issued by the responsible areas,
- Number of suggestions implemented (quantity/month),
- Planned and actual maintenance costs,
- Tracking of energy and water consumption (value/unit).
All the indicators above have their targets set by senior management (Hoshin) and communicated in the previous year, so that each area can do its planning and present its A3 document explaining how it will achieve the objectives.
In the “Key Points” field (see figure 6, item “c”), each production area had to report the main activities or kaizens carried out (see figure 7) or in progress needed to reach the established targets, and in the “Outlook” field PPC posted messages commenting on the plant's overall performance against the stipulated targets.

Figure 7: Kaizen examples
3. TRACKING THE INDICATORS
At the process level, leaders, supervisors and managers monitored each of the indicators described through charts updated daily (see figure 8) and displayed on “boards” for visual management (see figure 9).

Figure 8: Monitoring chart of productivity vs. downtime

Figure 9: Board for visual management of indicators
Source: Alcoa – II Forum Lean NE (2007)
Based on the target set in the A3 Monthly Report ( “Monthly Report”) and the daily analysis of indicators at the process level, failure to meet what had been established also triggered the “help chain”, so that problems or waste could be analyzed and action taken according to urgency or need.
At the plant level, the indicators were tracked in monthly senior management meetings, and indicators below target were analyzed and discussed by all areas present, so that everyone could engage with the difficulties and share ideas or new actions.
4. CONCLUSION
Indicators for production stability are factors set by senior management to check the progress of work against what was planned, at the lowest possible cost. They are also important guides for leadership, since whenever they fall below the established targets (hoshin) they will show which measures must be taken urgently.
In our lean journey outside Toyota, we have seen that many companies have already put up visual management boards for indicators to monitor stability, but, as in the examples of production tracking boards, they are not as effective, because there is no habit of measuring frequently, reflecting and analyzing in order to understand the numbers, and, when necessary, making corrections to reach the objectives.
For this, discipline is extremely important and must be maintained so that there is measurement, reflection and discussion among those involved whenever there are deviations, triggering redirection for the whole company.
When we look at the scientific method of “PDCA”, measuring the indicators would be the “C” for “check”, and most companies starting the lean journey do not even get to measure their results, or they fool themselves with indicators that do not represent reality. Most plan (“P”), do (“D”) and stop there. If there is no measurement and consequent reaction (“A”) in a continuous and repeated way, the improvement cycle does not continue and we may keep making subjective decisions rather than the necessary ones.
And one last reflection: for many, measuring indicators may represent the end of a cycle, but for lean thinkers it is the beginning of a new cycle of improvements which, if sustained by standardization, will bring great gains over time.